Building Timeline
2001
January 7
Submit Loan Application. to District Mission Board [DMB] and Real Estate Office [REO]
January 8-12
Get basic site plan and building plan as finalized as
currently possible w/architect.
January 15-19
Get with developer and receive their approval of our plans
- Meet with Madison City Departments to get feedback
January 21
-Congregation meeting- approve the basic design concept.
-Forward our plans to the Real Estate Office [REO], WELS Architectural Consultant, Board for Home Missions [BHM], DMB, and Builders for Christ [BFC]. Get feedback and make changes if needed.-submit financial statements to the Church Extension Fund [CEF]
-sign contract with Architect Danny Osborn
-Have congregation approve and then send application to BFC.
Early February
BHM Meeting- we receive planning authority and have our 5 year MPGA approved.
April
-23rd Builders for Christ [BFC] approves our application
-29th Early childhood education feasibility study is completed.
May
-We finalize our building plans [having considered the education feasibility study].
-We send our stuff to the REO for final review and approval.
-Loan applications and commitment letters are exchanged. We make sure to have our 1% loan fee and down payment in our CEF for easy transfer upon approval.
-Get BFC committees going.
June
Working drawings are completed. Sent in for review.
August
Project sent out to be bid.
2002
November 01- January 02
Permits received and Ground is broken and site prep/slab
pouring completed
Late June
Congregation projects including kitchen, landscaping, and irrigation.
July
Occupy building. First service.